India's State Minister for Defence, Dr. Subhash Bhamre outlines the progress of Tejas in a written reply to Dr. R. Lakshmanan in Rajya Sabha today.
Two contracts were signed between Indian Air Force (IAF) and Hindustan Aeronautics Ltd., (HAL) for procurement of (i) 20 Initial Operational Clearance (IOC) standard aircraft (16 IOC fighters and 4 IOC trainers) on 31st March 2006 to be completed by December 2011 and (ii) 20 Final Operational Clearance (FOC) standard aircraft (16 FOC fighters and 4 FOC trainers) on 23rd December 2010 to be completed by December 2016.
At the time of placement of IOC order in 2006, it was expected that Aeronautical Development Agency (ADA), who is the Programme Management Agency will obtain IOC in 2008 after which delivery was planned till December 2011. However, IOC has been achieved by ADA in December 2013 that too only for 16 fighter version IOC aircraft, after which only, HAL could take up production and first IOC fighter aircraft was delivered in 2016-17.
Till date, out of total 16 IOC fighter aircraft, 12 fighters have been delivered to IAF. HAL plans to deliver the balance 4 IOC fighter aircrafts by March, 2019. ADA has handed over Drawing Applicability List (DAL) and Equipment Standard of Preparation (SOP) documents, for FOC configuration to HAL on 31st December, 2018 duly cleared by centre of Military Airworthiness and Certification (CEMILAC) to go ahead with the production of FOC fighter aircraft. Accordingly HAL has taken up the production of LCA, FOC fighter aircraft.
The production of 8 trainer aircraft (4 each in IOC & FOC contracts) would be taken up only after design clearance from ADA. In order to fast track the delivery of LCA Tejas, the following steps have been taken:
|
|
|
|